Work is ongoing to reactivate the services of the CNAF Tier-1 data center. Right now an electrical line has been activated and since January 15th an UPS apparatus is working to cover up to 300 kW (of the overall 1.2 MW power needed by the whole data center). In this way, it is finally possible to restart some services. The recovery activity from the disks corrupted as a result of the flood occurred on last November 9th has been started. Data will be put on new disks. The cleaning activity of the tape library is almost complete. On January 17th the vendor will start the re-certification phase. In the meanwhile, […]